LPG Import Terminal for Power Generation

Written by | Nov 11, 2017 7:18:05 AM

28 MW Power Plant Expansion

  • Roatan Electric Company, Bay Islands, Honduras:
  • (12) 90,000 liquid propane storage tanks
  • (1) 200,000 gallon tank to fuel existing power plant
  • Ship & barge unloading
  • Completion time: 6 months.